This week’s progress includes exterior site work, retaining wall and fire service upgrades, and brick and sidewalk installation on the new addition at Wading River Elementary School. The interior work at WRES continues with new bathroom tile and classroom casework.

Miller Avenue’s bright interior features a new ceiling, mechanical duct work, painting and new flooring, while the outside work saw the installation of new curbs and preparation for the sidewalk.

The fall sports season is gearing up at Prodell Middle School with the installation of track surfacing and athletic field grading.